Exercise Pitch Black Accommodation Camp

Industry


Commercial

Contract (budget)


$1,896,250.00

Delivery


4 months

Brief:

Transportable Solutions was engaged to design and manufacture 20 12m x 3m Office Units with 3 step stair case/landings suitable for high traffic areas on RAAF Base Darwin to assist in accommodating Defence personnel for the Pitch Black exercise.


Scope of work:

  • Detailed design, including all structural, mechanical and electrical components
  • Manufacture 20 identical buildings including all electrical and mechanical FF&E
  • Secure Buildings to ensure safe and prepare for transportation
  • Manufacture 20 identical 1200mm Stair cases and Landings


Challenges:

  • Managing tight timeframes to meet the clients needs, securing a bulk supply of essential materials 
  • Coordinating with the contracted company who were in charge of collecting, transporting and onsite installations of our buildings.


Solutions:

Transportable Solutions fostered strong collaboration with industry partners and suppliers ensuring they were well informed about the programs progress and requirements, enabling them to meet necessary timeframes. Everyone involved demonstrated exceptional commitment to ensure the availability of quality products when needed. Our team of skilled carpenters and labourers went above and beyond maintaining.


Transportable Solutions NT’s reputation for quality builds
The strength of communication between our project team and suppliers enabled the success of early handover for the required 20 custom staircases and landings. This meant onsite occupancy was able to happen 1 week earlier than the original program which also assisted Defence Personnel to commence their exercise requirements ahead of schedule.



A man in a yellow shirt is standing in front of a yellow crane.
A long hallway with a fire extinguisher in the middle of it.
A row of trailers are parked in a dirt field.
By Justine David August 21, 2024
Design and manufacture an additional 28 identical four-bedroom accommodation units with ensuites. This project also involved the fabrication and design of walkway verandas with fire-rated decking to meet Bushfire Attack Level (BAL) requirements.
A 3d model of a house with a porch and stairs
By Justine David August 21, 2024
Design and manufacture a large customised multi-purpose facility comprising 10 modular units.
A woman is standing in front of a construction site holding a clipboard.
April 19, 2024
In the traditionally male-dominated world of construction, women are increasingly taking center stage, reshaping the industry's landscape and driving innovation across Australia. From building sites to boardrooms, women are making their mark in roles once considered off-limits, challenging stereotypes and paving the way for a more inclusive future.
There are trees in the middle of a dirt field.
April 19, 2024
In the vast expanse of Northern Australia, where the landscape is as diverse as the challenges it presents, modular construction stands out as a beacon of innovation. From remote communities to bustling urban centres, the demand for adaptable building solutions has never been greater. However, navigating the unique obstacles of the Northern Territory requires a deep understanding of the region's environment and culture. Let's delve into the challenges and solutions inherent in modular construction in this dynamic setting.
A man is standing next to a truck that says oversized on the back.
April 19, 2024
In the rugged expanses of the Northern Territory, commercial construction projects often face unique challenges. However, amidst these challenges lies a solution that is revolutionising the way commercial buildings are constructed – modular construction. Here are five compelling benefits of using commercial modular construction in the Northern Territory:
A man in a yellow shirt is standing in front of a yellow crane.
April 16, 2024
Constructing a 14.4m x 3.3m M/F Ablution with disabled access, including a full-length veranda and sustainable decking.
A crane is lifting a building in a parking lot
April 16, 2024
Designing and building 50 accommodation units posed challenges with tight deadlines, material sourcing, and labor allocation.
A small house with stairs leading up to it
April 15, 2024
Transportable Solutions undertook its inaugural project, crafting five 8.4 x 3.5 laundry units, strategically meeting the burgeoning demands of our client.
A small house with a ramp and a sign in front of it.
April 8, 2024
Design and construction of a custom-made kiosk for the community pool in Wadeye.
Share by: